Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam CBAP topic 1 question 3 discussion

Actual exam question from IIBA's CBAP
Question #: 3
Topic #: 1
[All CBAP Questions]

All of the following stakeholders participate in the prioritization of requirements except for which one?

  • A. Implementation subject matter expert
  • B. Project team
  • C. Domain subject matter expert
  • D. Project manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Farooq_95
2 weeks, 6 days ago
Selected Answer: B
The project team typically does not participate in setting the priority of requirements; their role is to execute the prioritized deliverables. As per BABOK v3 5.3.7, all others may be involved in prioritization.
upvoted 1 times
Farooq_95
2 weeks, 6 days ago
Domain SME is not mentioned in BABOK v3 5.3.7, but Domain subject matter experts (SMEs) can assist in prioritizing requirements by providing insights into the business domain, understanding the impact of each requirement on business objectives, and assessing the urgency of implementation based on domain-specific factors. They can help evaluate the feasibility and practicality of implementing certain requirements within the existing business context.
upvoted 1 times
...
...
Uloaku
1 year, 11 months ago
Answer is B. Babok V3 page 90
upvoted 2 times
...
Dillon91
2 years, 1 month ago
I also believe B
upvoted 1 times
...
NickMane
2 years, 10 months ago
B&C are not stakeholders BABOK v3: 5.3 - Prioritize requirements
upvoted 3 times
...
nrp26
3 years, 1 month ago
Ans is B. Domain SME's are stakeholders. Refer the errata document which addresses this: https://www.iiba.org/career-resources/a-business-analysis-professionals-foundation-for-success/babok/babok-guide-errata/
upvoted 2 times
...
rhsdeal
3 years, 1 month ago
This is a Babok v2 question in the v2 guide pg 103 the stakeholders for prioritize requirements are: 6.1.6 Stakeholders Domain SME: Domain subject matter experts may be invited to participate in the prioritization of requirements, to assess the relative business need, and to negotiate their importance. Implementation SME: Implementation subject matter experts may be asked to evaluate the relative complexity or risk associated with the implementation of certain requirements. Project Manager: The project manager is responsible for the implementation of the solution and will use the priority of requirements as an input into the project plan. Sponsor: Since sponsors are ultimately accountable for the business solution and major project decisions, they need to be invited to participate in the discussion. For v-3 Pg. 90 states the stakeholders of prioritization of requirements are: Customer, End User, Implementation Subject Matter Expert, Project Manager, Regulator, Sponsor.
upvoted 2 times
...
HappyA
3 years, 3 months ago
Ans is C Domain SME as per pg 90
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...