Exam PMP topic 1 question 126 discussion

Actual exam question from PMI's PMP
Question #: 126
Topic #: 1
[All PMP Questions]

A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?

  • A. Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy
  • B. Add the missing budget items to the risk log and present them in the next project steering committee
  • C. Start the project and deal with these budget issues as they arise throughout the project life cycle
  • D. Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
52d1fe0
2 weeks, 4 days ago
Selected Answer: A
project sponsor approved the project charter. When the budget is missing from the charter, discuss with the sponsor.
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: A
A. Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy
upvoted 2 times
...
TPObee
1 year, 1 month ago
A is a good answer. Any opinion on B?
upvoted 1 times
suflam3
1 year, 1 month ago
Major budget item that is necessary for project completion, hence this is not a risk that can be avoided/mitigated. B is not suitable in this context.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...