Question #: 666
Topic #: 1
[All PMP Questions]

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the project manager do?

  • A. Perform schedule analysis.
  • B. Perform quality control analysis.
  • C. Perform trend analysis.
  • D. Perform root cause analysis (RCA).
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
cwilson91
Highly Voted 11 months ago
Selected Answer: C
Schedule Analysis: Schedule analysis focuses on evaluating the project schedule and comparing it to the actual progress of the project. It involves analyzing the planned activities, their sequence, duration, and dependencies, and comparing them to the actual progress achieved. The purpose of schedule analysis is to identify any variances or deviations from the planned schedule and assess the impact on the project timeline. Trend Analysis: Trend analysis, on the other hand, focuses on examining project performance data over time to identify patterns, trends, or tendencies. It involves analyzing historical data and project metrics to identify recurring patterns or trends in various aspects of the project, such as cost, schedule, quality, or team performance. Trend analysis helps project managers understand the project's overall direction and make predictions about future performance.
upvoted 8 times
...
DD_PMP
Most Recent 2 weeks, 4 days ago
A. Checking to see slippages will entail performing the schedule analysis
upvoted 1 times
...
victory108
7 months, 2 weeks ago
Selected Answer: C
C. Perform trend analysis
upvoted 1 times
...
miggykurkova
8 months, 1 week ago
trend analysis uses historical results to predict future outcome
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...