Exam PgMP topic 1 question 6 discussion

Actual exam question from PMI's PgMP
Question #: 6
Topic #: 1
[All PgMP Questions]

Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?

  • A. Teaming
  • B. Exploiting
  • C. Accepting
  • D. Sharing
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
LuanND
1 week, 1 day ago
Selected Answer: D
totally agree with D
upvoted 1 times
...
Ahsan_tirmizi
2 weeks, 3 days ago
yup sharing D
upvoted 1 times
...
mfshabana
6 months, 1 week ago
D. Sharing Creating a teaming agreement with a competing company is a form of risk sharing. Both organizations collaborate and share resources to address the challenges and opportunities associated with the program. This approach allows each company to leverage the strengths of the other, share responsibilities, and jointly manage the risks and rewards associated with the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted