A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
Martinussantika
1 week, 4 days agodebug91
2 weeks, 4 days agojiljap
2 weeks, 6 days agodjgdgaf
2 months, 2 weeks agodrimz
3 months agodrimz
3 months agojosephsafiran
4 months, 1 week agoGabMonterey
5 months, 1 week agow_b_m
6 months, 1 week agoJaya12
6 months, 2 weeks agoLucky_Cindy
7 months agoDavid983
7 months, 1 week agoDavid983
7 months, 1 week agoTuanit
7 months, 1 week agoLoan
9 months agoSteAle
10 months, 3 weeks agovictory108
11 months, 1 week agoJMCCRAY
1 year agoDedutch
1 year, 1 month ago