A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
8a6d137
1 month, 3 weeks agopigmeatpig
3 months, 2 weeks agod67fcef
4 months, 3 weeks agoWWu
5 months agoWWu
6 months, 2 weeks agoWWu
5 months agobetterthanyesterday
7 months agoductrinh
3 months, 2 weeks agokavikris
7 months, 1 week agoMartinussantika
1 year, 2 months agodebug91
1 year, 2 months agojiljap
1 year, 2 months agodjgdgaf
1 year, 4 months agodrimz
1 year, 4 months agodrimz
1 year, 4 months agojosephsafiran
1 year, 6 months agoGabMonterey
1 year, 7 months agow_b_m
1 year, 8 months agoJaya12
1 year, 8 months agoLucky_Cindy
1 year, 8 months ago