During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment.
What type of analysis should the project lead have conducted to avoid this situation?
elrexyeoh
1 week, 4 days agoBruce_Liu
3 months, 3 weeks agojosephsafiran
3 months, 3 weeks agovatsan1980
4 months, 2 weeks agoexamkitten
5 months, 2 weeks agoLucky_Cindy
6 months, 1 week agoChezQW
6 months, 1 week agoOnly12go
6 months, 2 weeks agojon0729
6 months, 2 weeks agoadingmaki
6 months, 2 weeks agovictory108
8 months, 3 weeks agoSteAle
10 months, 1 week agoaqz_111
11 months, 3 weeks agoJYKL88
1 year agoJYKL88
1 year agoHung3102
1 year, 1 month agoRagazzoAlex
1 year, 2 months agoBAKH
1 year, 3 months ago