Exam PSM I topic 1 question 50 discussion

Actual exam question from Scrum's PSM I
Question #: 50
Topic #: 1
[All PSM I Questions]

What two factors are best considered when establishing the Sprint length? (Choose two.)

  • A. The organization has mandated similar length sprints.
  • B. The level of uncertainty over the technology to be used.
  • C. The frequency at which team formation can be changed.
  • D. The risk of being disconnected from the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maverick_walker
2 weeks, 4 days ago
B & D are correct
upvoted 1 times
...
Mi_Windsor
9 months, 1 week ago
B and D are correct
upvoted 1 times
...
Pinha
1 year ago
BD D is clear! The level of uncertainty over the technology to be used affects the Sprint length because it determines how much time the team will need to explore and experiment with the technology before they can deliver a valuable product increment. If the technology is well understood, then the Sprint length can be shorter, but if there is a lot of uncertainty, then a longer Sprint length may be needed.
upvoted 4 times
...
amog
3 years, 3 months ago
B and D are correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...