Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
sale

Want to Unlock All Questions for this Exam?

Full Exam Access, Discussions, No Robots Checks

Oracle 1z0-1066-22 Exam Actual Questions

The questions for 1z0-1066-22 were last updated on April 15, 2024.
  • Viewing page 1 out of 14 pages.
  • Viewing questions 1-4 out of 55 questions

Topic 1 - Exam A

Question #1 Topic 1

How does the Demand Fulfillment view prioritize at-risk demands?

  • A. Based on the order value per customer weighted by the number of associated recommendations required to make the demand no longer at risk
  • B. Based on order value weighted by the number of compression days required to make the demand no longer at risk
  • C. Based on order value weighted by the number of associated recommendations required to make the demand no longer at risk
  • D. Based on the number of associated recommendations required to make the demand no longer at risk
Reveal Solution Hide Solution   Discussion  

Correct Answer: C 🗳️

Question #2 Topic 1

Which statement order is NOT true about how to effectively address demand at risk?

  • A. Recommendations appear in one of these five categories (or tabs): Expedite Buy Orders, Expedite Planned Orders, Expedite Transfer Orders, Add Resource Availability, and Add Supplier Capacity.
  • B. When you accept an expedite recommendation, the order is firmed by using the expedite date as the firm date. So when the plan is run after accepting the recommendation, the planning process assumes the supply is available on the firm date.
  • C. Be aware that recommendations to expedite buy orders not only include purchase orders and requisitions, but also planned buy orders.
  • D. To maximize effort, use the Recommendations Summary graph and aim for a low number of recommendations with the associated at-risk demand value substantial enough to make a difference in demand fulfillment percentage.
Reveal Solution Hide Solution   Discussion  

Correct Answer: A 🗳️

Question #3 Topic 1

Which two statements are true about Production Scheduling? (Choose two.)

  • A. Schedule options include: Configure Scope, Parameters, and View Settings.
  • B. Releasing a schedule can update Manufacturing Cloud work orders with revised dates, resources, release status, and work definitions.
  • C. Refreshing a Production Schedule means that the schedule is being recalculated.
  • D. A resource’s constraint mode has two choices: Relaxed and Constrained.
  • E. If a work order is not firm, Production Scheduling may schedule with an alternate resource.
Reveal Solution Hide Solution   Discussion  

Correct Answer: AE 🗳️

Question #4 Topic 1

Which statement is true about the Production Scheduling Gantt chart?

  • A. The Gantt chart is read only, but you can change colors, sizing, and perform filtering.
  • B. You can view a Gantt chart or the Dispatch List, but not both at the same time.
  • C. The Gantt chart identifies idle time, changeovers, and downtime.
  • D. Metrics displayed above the Gantt chart include Late Demands, Late Work Order, Early Work Orders, and Changeover Time.
Reveal Solution Hide Solution   Discussion  

Correct Answer: C 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...