Question #: 434
Topic #: 1
[All CSCP Questions]

A work center's demonstrated capacity for the last week was 160 standard hours. Its demonstrated capacity for the last 6 weeks was 140 standard hours. Which of the following numbers would be best to use to determine the appropriate future load for the work center?

  • A. 160 standard hours, because it reflects what the work center has proven it can do
  • B. 160 standard hours, because it reflects what happened most recently
  • C. 150 standard hours, because it is the average of the last two periods
  • D. 140 standard hours, because it is based on a greater number of periods
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Rajiv8047
2 weeks, 2 days ago
Selected Answer: D
140 standard hours, because it is based on a greater number of periods. This choice is more conservative and is based on a longer period which might give a more stable and reliable measure of the work center's capacity. It takes into account more data points, which likely includes weeks of both higher and lower performance, thus giving a more rounded view of the work center's capacity.
upvoted 1 times
...
igrd
1 year ago
Selected Answer: C
The number that would be best to use to determine the appropriate future load for the work center is 150 standard hours, which is the average of the last two periods. While the demonstrated capacity for the last week was higher than the demonstrated capacity for the last 6 weeks, it is important to consider a longer time horizon to account for any potential variability or seasonality in the work center's capacity. By taking an average of the last two periods, businesses can gain a more accurate understanding of the work center's recent performance and make more informed decisions about future capacity planning.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...