Exam CSCP topic 1 question 292 discussion

Actual exam question from APICS's CSCP
Question #: 292
Topic #: 1
[All CSCP Questions]

An operations manager wants to measure variability in the delivery time of insurance policies to clients. Which of the following quality tools most appropriately would show the level of variability?

  • A. Pareto chart
  • B. Histogram
  • C. Scatterplot
  • D. Check sheet
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kaushal_Pandey
2 years, 9 months ago
Amount and range of variation with in a process is shown by Histogram
upvoted 3 times
...
Sanjey
3 years, 3 months ago
Question asks for 'Level of variability' that can be shown by Scatter chart. Histogram helps in categorising, seggregating
upvoted 1 times
Nowaz
2 years, 1 month ago
Incorrect. The scatter chart shows the strength of a relationship between two variables on an x and y axis chart. A histogram "buckets" outcomes by the number of occurrences of those outcomes
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...