Exam PSP topic 1 question 18 discussion

Actual exam question from ASIS's PSP
Question #: 18
Topic #: 1
[All PSP Questions]

Which of the following are the stages of the project management?

  • A. Design, development, execution, and closeout
  • B. Design, initiation, implementation, and closeout
  • C. Initiation, development, implementation, and closeout
  • D. Feasibility, development, execution, and closeout
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
lin12345678
Highly Voted 1 year ago
Selected Answer: D
please check out official guide
upvoted 6 times
...
Casey04
Most Recent 10 months, 3 weeks ago
D is correct, see IPPS, page 36-37
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
ex Want to SAVE BIG on Certification Exam Prep?
close
ex Unlock All Exams with ExamTopics Pro 75% Off
  • arrow Choose From 1000+ Exams
  • arrow Access to 10 Exams per Month
  • arrow PDF Format Available
  • arrow Inline Discussions
  • arrow No Captcha/Robot Checks
Limited Time Offer
Ends in