Which of the following items are part of the planning phase of project management?

  • A. Bidder's instructions and business objectives
  • B. Technical evaluations and equipment lists
  • C. Bidder's conference and cost evaluations
  • D. Threat assessment and design criteria
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Casey04
1 year, 2 months ago
D is correct - see IPPS pages 27 and 68
upvoted 2 times
...
d7703
1 year, 3 months ago
a risk assessment report and design criteria are outputs of the planning phase
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...