Question #: 333
Topic #: 1
[All CMQ-OE Questions]

A benefit-cost analysis can best be used to:

  • A. align project costs with original budget forecasts
  • B. evaluate the performance of project team members
  • C. compare the performance of different project teams
  • D. compare savings earned against resources invested
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ZeroLord
2 days, 13 hours ago
Selected Answer: D
I think the best answer is D, since Benefit-cost analysis does not relate to team memebers performance answers B or C, or project cost with budget (CPI) answer A.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel