At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
This section is not available anymore. Please use the main Exam Page.RCDD-001 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CUB90
1 year, 5 months ago