Exam RCDD-001 topic 13 question 14 discussion

Actual exam question from BICSI's RCDD-001
Question #: 14
Topic #: 13
[All RCDD-001 Questions]

At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?

  • A. The project is under budget.
  • B. The project is budget incorrect.
  • C. The project has been back-end loaded.
  • D. The project is over budget.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
CUB90
5 months, 2 weeks ago
TDMM page 21-26 (1557)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...