During the initial scoping of a project, a data model can be used to:

  • A. Determine the security requirements for accessing the data
  • B. Determine the impact of business processes and customer lifecycles
  • C. Identify detailed impact on all the tables in a database that must be changed
  • D. Provide a clear definition of affected and non-affected data entities
  • E. Plan the structure of the metadata repository
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ajeeth180
2 weeks, 1 day ago
Selected Answer: D
During initial project scoping, the data model helps clarify which data entities will be impacted by the project and which will not. This is essential for: Scoping the extent of data-related changes Estimating effort and cost Aligning with stakeholders and system owners
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...