exam questions

Exam 300-510 All Questions

View all questions & answers for the 300-510 exam

Exam 300-510 topic 1 question 76 discussion

Actual exam question from Cisco's 300-510
Question #: 76
Topic #: 1
[All 300-510 Questions]

Refer to the exhibit.



A network engineer configured routers R1 and R5 to run in IS-IS Level 1 mode and router R6 to run in IS-IS Level 2 mode. All other routers are running as Level 1 / Level 2 routers. An engineer expects traffic from R1 to R6 to pass via R2, but IS-IS routing has calculated the best path via R4. Which action corrects the problem?

  • A. Configure all routers as Level 1 routers.
  • B. Remove the link metric for the link from router R1 to router R2.
  • C. Change the link metric for the link from router R1 to router R2 to 1.
  • D. Configure all routers as Level 1 / Level 2 routers.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
veryfab12345
10 months, 1 week ago
Selected Answer: C
The Level-1 Area ends at R4 and R3. Keep in mind that default metric in ISIS is 10. So the link R1 to R4 is 10. R1-R2-R3 is 16. So R4 is the better exit. When changing R1-R2 to metric 1, the total metric to the exit point R3 is 9 and now preferred.
upvoted 2 times
...
thejag
11 months, 1 week ago
Selected Answer: C
Correct is C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel