An engineer associates EPG-A with a VMM domain and sets the Deployment and Resolution preferences to Immediate. The host that will generate endpoints for EPG-A is attached to Leaf-101 and Leaf-102 using etht1/1. However, no configuration for EPG-A appears to have been pushed to the leaf switches. Which action must be taken for the configuration to be pushed to Leaf-101 and Leaf-102?