An engineer is informed that high availability for a Cisco IM and Presence server fails. While the engineer examines the Cisco UCM presence redundancy group in the UI, they discover that the first node is in the Idle state, and the second node is in the running in backup mode state. Which action must the engineer take to place both nodes back in the normal state?

  • A. Restart the first node of the IM and Presence server.
  • B. Click Failover in the Server Action field.
  • C. Click Fallback in the Server Action field.
  • D. Reinstall the first node of the IM and Presence server.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
spud9000
7 months ago
Selected Answer: C
https://www.cisco.com/c/en/us/td/docs/voice_ip_comm/cucm/im_presence/configAdminGuide/10_0_1/CUP0_BK_C318987B_00_config-admin-guide-imp-100/cup0_mp_t32463d1_00_troubleshooting-high-availability.html#CUCM_TK_I93090B4_00
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago