Question #: 201
Topic #: 1
[All 300-425 Questions]

A company installs a new anchor controller in the DMZ. The company has not upgraded the foreign controller for several years. The foreign controller runs code 7.5. The IT administrator suggests that the company upgrade the foreign controller and the new anchor controller to 8.10 or later. Which two benefits must be incorporated into the design regarding the code upgrade? (Choose two.)

  • A. The foreign controller load balances guest clients across the list of anchor controllers
  • B. Guest clients are load balanced in round-robin fashion among the anchor controllers.
  • C. User devices must upgrade their WLAN card drivers.
  • D. Guest clients are tunneled to anchors with the highest priority.
  • E. The foreign controller designates one anchor as primary and one or more anchors as secondary.
Show Suggested Answer Hide Answer
Suggested Answer: AE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
55f2ace
2 months ago
Selected Answer: AD
https://www.cisco.com/c/en/us/td/docs/wireless/controller/8-1/Enterprise-Mobility-8-1-Design-Guide/Enterprise_Mobility_8-1_Deployment_Guide/WirelessNetwork_GuestAccessService.html
upvoted 1 times
...
Farhad123
2 months, 2 weeks ago
Selected Answer: AE
A and E are the right choices, we can load balance clients between WLCs also designate one WLC as primary and another as secondary
upvoted 1 times
...
AdamNoe
3 months ago
Selected Answer: DE
Releases Prior to 8.1 All guest clients are load balanced in round robin fashion amongst anchor WLCs. If an anchor fails, guest clients will be load balanced amongst remaining anchor WLCs. With Release 8.1 All guest clients are sent to anchor controller with highest priority in relation to local internal WLC. If an anchor fails, guest clients will be sent to the next highest priority or round robin if remaining anchors have same priority value.
upvoted 1 times
...
Rododendron2
6 months ago
Selected Answer: AD
A+D , 8.1 and higher - clients go to anchor with highest priority, if same priority then load balanced
upvoted 1 times
...
ShamsDimashki
9 months, 1 week ago
Selected Answer: AE
A and E are correct
upvoted 2 times
...
TonyVi
9 months, 1 week ago
Correct Answer A and E A. The foreign controller load balances guest clients across the list of anchor controllers: Upgrading to version 8.10 or later provides the ability for the foreign controller to distribute guest clients across multiple anchor controllers. This helps to optimize network resources and ensures better performance and reliability by preventing any single anchor controller from becoming a bottleneck. Primary and Secondary Anchor Designation: E. The foreign controller designates one anchor as primary and one or more anchors as secondary: With the newer code, the foreign controller can designate a primary anchor controller and one or more secondary anchor controllers. This provides redundancy and ensures that if the primary anchor controller fails, the secondary controllers can take over, thus maintaining service availability for guest clients.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago