Question #: 251
Topic #: 1
[All 400-007 Questions]



Refer to the exhibit. After a network audit a network engineer must optimize the current network convergence time. The proposed solution must consider link layer and control plane failures.

Which solution meets the requirements?

  • A. Configure debounce timers
  • B. Increase fast hello timers
  • C. Implement BFD
  • D. Enable LSP fast flood
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Devsin2000
2 months, 1 week ago
Selected Answer: B
I think his is a very tricky question. Generally speaking C(BFD) would be right choice, however "solution must consider control plane failure". I am not sure if BFD are directly part of IS-IS control plane.
upvoted 1 times
...
Doobiedoo
8 months, 3 weeks ago
Selected Answer: C
BFD is correct. It detects the peer is down at layer2, and notifies the routing processes. The IS-IS process gets the "Peer Unreachable" event and immediately tears down the peering without waiting for the IS-IS timers to expire.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago