A customer is implementing a business continuity solution for the current data centers. The new location must mitigate the impact of a disaster in any existing data centers by providing an acceptable level of service. The solution must support:

• fully segregated Layer 2 and 3 fault domains
• low or no human intervention for service restoration
• medium to high RPO/RTO for a subset of applications
• asynchronous storage replication for application data

Which disaster recovery solution must the customer select to meet these requirements?

  • A. mirrored inactive infrastructure facility with fully stretched resources
  • B. cold infrastructure facility with basic infrastructure
  • C. identical infrastructure facility ready to provide service
  • D. partially equipped infrastructure facility for on-demand activation
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chad0128
4 weeks, 1 day ago
Selected Answer: D
Going with D as the question states " by providing an acceptable level of service"
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...