An administrator is replacing a fabric interconnect. The failed fabric interconnect was FI-A and was master at the time of failure. Which process brings the replacement fabric interconnect into the cluster?
A.
Connect the new FI-A to the management network and the Layer 1/Layer 2 links to the existing FI-B. Use the Full State Backup file to restore the configuration when prompted at the console.
B.
Connect the new FI-A to the management network and the Layer 1/Layer 2 links to the existing FI-B. Let the system sync with FI-B when prompted at the console.
C.
Connect the FI-A to the management network and the Layer 1/Layer 2 links to the existing FI-B. Use the All Configuration backup file to restore the configuration through Cisco UCS Manager GUI.
D.
Connect the new FI-A to the management network only. Use the Full State Backup file to restore the configuration through Cisco UCS Manager GUI. Connect the Layer 1/Layer 2 cables.
E.
Connect the new FI-A to FI-B using the Layer1/Layer 2 cables only. Sync the configuration when prompted. Connect the management interface when the configuration is synced.
Still toggling between B und E. Usually you start with updating firmware in standalone mode and therefore you need the mgmt port, and then you need to erase the config. The second FI will not switch back automatically, so whats the issue with cabling the mgmt port ?
This section is not available anymore. Please use the main Exam Page.400-151 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MasterDebug
5 years, 5 months agomojzucha