Question #: 500
Topic #: 1
[All N10-008 Questions]

An organization would like to implement a disaster recovery strategy that does not require a facility agreement or idle hardware. Which of the following strategies MOST likely meets the organization’s requirements?

  • A. Cloud site
  • B. Cold site
  • C. Warm site
  • D. Hot site
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
LayinCable
Highly Voted 1 year ago
Selected Answer: A
They want no binding contract with a building and they want no hardware, therefore Cloud is the best and only option the company wants.
upvoted 5 times
...
Tasiaa4l
Most Recent 7 months ago
This is on the test for sure
upvoted 2 times
...
Eumousten
1 year ago
Selected Answer: A
That does not require a facility agreement or idle hardware
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago