Actual exam question from CompTIA's PK0-005
Question #: 4
Topic #: 1
[All PK0-005 Questions]

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

  • A. Evaluating the project
  • B. Releasing the resources
  • C. Closing the contracts
  • D. Reconciling the budget
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SkylarC
Highly Voted 2 years, 1 month ago
Selected Answer: D
D. Reconciling the budget is an activity that should be used in the closing phase of a project to support the project triple constraint. The project triple constraint refers to the relationship between scope, time, and cost in a project. Reconciling the project budget at the closing phase of a project ensures that all expenses have been accounted for, and the final budget is reconciled with the actual expenses, which is crucial to measuring cost performance. Evaluating the project is an activity that should be conducted throughout the project and not just in the closing phase. The purpose of evaluating the project is to determine whether the project was a success or failure, or if there are any areas that require improvement.
upvoted 8 times
...
lamborghini
Highly Voted 8 months, 3 weeks ago
Selected Answer: A
I think it's A. The evaluation process should include a review of the project's scope, schedule, and budget. The project manager should also review the project's deliverables to ensure that they meet the requirements of the project. The evaluation process should also identify any lessons learned that can be applied to future projects. By evaluating the project at the end of the project, the project manager can help to ensure that the project triple constraint has been met and that the project has been a success. Budget Reconciliation focuses on the project's financial performance.
upvoted 5 times
...
Networks210
Most Recent 7 months, 1 week ago
Selected Answer: A
A. Evaluating the project: This activity directly supports the project triple constraint by assessing whether the project met its scope, stayed within budget, and adhered to the timeline. Evaluating the project involves analyzing performance and results, which helps determine if the project was successful within the constraints and provides insights for future projects. D. Reconciling the budget: While important, budget reconciliation is typically done in the monitoring and controlling phase to ensure ongoing alignment with budget constraints. By the closing phase, budget reconciliation should already be completed, so this isn't as relevant as evaluating the project's overall performance.
upvoted 1 times
...
dhamm
8 months, 3 weeks ago
Selected Answer: D
The answer is D. Reconciling the budget. The project triple constraint refers to the three interrelated factors that must be balanced in order to successfully complete a project: time, scope, and cost. Reconciling the budget is an activity that ensures that the project's actual costs match the planned costs, which helps to ensure that the project is on budget.
upvoted 1 times
mx007
1 year, 8 months ago
Budget is only about cost. So no Triple Constrain
upvoted 2 times
...
...
Caoilfhion
8 months, 3 weeks ago
Selected Answer: A
It is A, because it's asking for the "triple" constraint (3 things, not one). Reconciling is just one thing, satisfying the cost. The other two options on the list actually satisfy the other conversations of scope and time (turning out resources no longer needed reducing scope, finishing contracts that specify the expected schedule of the project reducing time). So, therefore, evaluation process allows us to hit all three actions by showing us these needed actions, wrapping it up in a nice "triple" package. (Answer A)
upvoted 2 times
OzProphecies
1 year, 4 months ago
I'm going to trust you. My future is in your hands!
upvoted 2 times
...
...
TheFai
1 year, 2 months ago
Selected Answer: D
Reconciling the budget is the only one that makes sense.
upvoted 1 times
...
AdmiralGimme
1 year, 3 months ago
Selected Answer: A
Chat GPT said C, but I think that is wrong. If you are doing something on the triple constraint, it should involve all three aspects equally...so Evaluating the Project would address more of the triple constraint So, D. = Budget obviously and C. = is budget/scope. A. reviews the budget/scope/time.
upvoted 1 times
...
JBD
1 year, 9 months ago
The activity that should be used in the closing phase of a project to support the project triple constraint is evaluating the project (option A). In this phase, the project team assesses the project's performance against the initial objectives, scope, schedule, and budget. This evaluation helps identify any variances or deviations from the original plan and enables the team to determine the project's overall success. Releasing resources (option B), closing contracts (option C), and reconciling the budget (option D) are also important activities in the closing phase, but evaluating the project directly supports the project triple constraint.
upvoted 1 times
...
BlueMan93
2 years, 1 month ago
Selected Answer: D
Triple Constraint = scope, time, cost
upvoted 3 times
mx007
1 year, 8 months ago
Budget=cost, not scope or time
upvoted 1 times
...
...
7acdde5
2 years, 1 month ago
Selected Answer: D
D is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...