Actual exam question from CompTIA's PK0-005
Question #: 37
Topic #: 1
[All PK0-005 Questions]

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

  • A. Document the request in the change control log.
  • B. Communicate the change deployment.
  • C. Conduct an impact assessment.
  • D. Implement the change.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ExamNinja1
4 months, 1 week ago
Selected Answer: D
Tricky question. Don't let the approval throw you off. The last step that happened was "update the project plan", after that is implement. D
upvoted 1 times
...
MultanSean
8 months ago
Selected Answer: D
update the plan --> implement it by doing stuff
upvoted 1 times
...
eXhilarat3d
1 year ago
Selected Answer: B
Per AI source... B. Communicate the change deployment: It is essential to inform all stakeholders about the change and how it affects the project. This ensures that everyone is aware of the new end date and can adjust their plans and expectations accordingly. Documenting the request in the change control log is typically done before the change is approved. Conducting an impact assessment is part of the evaluation process before approving a change. Implementing the change is the final step after all necessary preparations and communications have been made.
upvoted 3 times
...
HappyG
1 year, 1 month ago
Selected Answer: D
They just updated the project plan so next is implement the change. The order is listed in the objectives.
upvoted 2 times
gorilla2001
8 months ago
"As a result of an approved change, the project manager updates the project plan with the newest project end date." The change was already approved and implemented; the next step is communicating the change. Answer is B.
upvoted 1 times
Illini
7 months, 3 weeks ago
Wrong. Implement the change. Look up change control process.
upvoted 1 times
...
...
...
DustyRex1
1 year, 2 months ago
Selected Answer: D
it's D, C is the very last step
upvoted 2 times
...
TheFai
1 year, 2 months ago
Selected Answer: D
The change has been approved, they now need to implement it. You communicate the change after it has been implemented.
upvoted 2 times
...
GrannyJune
1 year, 3 months ago
- Create/receive change requests -Document requests in the change control log - Conduct a preliminary review - Conduct impact assessments - Document change recommendations - Determine decision makers - Escalate to the change control board (CCB), if applicable - Document the status of approval in the change control log - Communicate the change status - Update the project plan - Implement changes - Validate the change implementation - Communicate change deployment The answer is D, which is the next step after updating the project plan. C is the final step in the process.
upvoted 4 times
GrannyJune
1 year, 3 months ago
*B is the final step in the process
upvoted 3 times
...
...
Boats
1 year, 5 months ago
Selected Answer: D
▪ Initiating the request ▪ Evaluating the impacts ▪ Making a decision on the outcome ▪ Implementing the change
upvoted 3 times
...
Granddude
1 year, 8 months ago
Selected Answer: D
I am changing my vote to D because in order it should be C, A, (Before the request) Approval, D, and then B after the request has been completed.
upvoted 2 times
...
Granddude
1 year, 9 months ago
Selected Answer: C
The problem I am seeing with B is that if C is not done first, it can cause delays for other departments. Such as their schedules and budgets, etc.
upvoted 1 times
...
JohnLarsen
1 year, 9 months ago
Selected Answer: B
Given that the change has been approved and the project plan updated, the next logical step would generally be to "Communicate the change deployment" (Option B). This ensures that all stakeholders are aware of the new project end date and can plan accordingly. Communication is vital at this stage to make sure that everyone is on the same page, helping to avoid confusion or issues later on.
upvoted 1 times
...
jksdbfb
1 year, 9 months ago
Selected Answer: B
Most likely going with B as well
upvoted 1 times
...
shakevia463
1 year, 11 months ago
Selected Answer: B
Once the project plan has been updated with the newest end date, the project manager should communicate the change deployment with stakeholders.
upvoted 1 times
...
TheGinjaNinja
2 years, 1 month ago
Selected Answer: B
I going to go with B
upvoted 3 times
TheGinjaNinja
2 years ago
The project manager should communicate the change deployment next after updating the project plan with the newest project end date as a result of an approved change. Communicating the change deployment involves informing all relevant parties about when and how the change will be implemented and what are the expected outcomes and benefits. Communicating the change deployment can help to ensure alignment, readiness, and support for the change and avoid any confusion or resistance.
upvoted 1 times
...
...
ITPRO90
2 years, 1 month ago
D is the correct answered.
upvoted 2 times
ITPRO90
2 years, 1 month ago
Reviewing the question and the study guide. B is correct.
upvoted 2 times
...
...
SkylarC
2 years, 1 month ago
Selected Answer: B
B. Communicate the change deployment should be completed NEXT after updating the project plan with the newest project end date. Once the project plan has been updated with the newest end date, the project manager should communicate the change deployment with stakeholders. This communication should inform them about the change, including the impact on project activities, timelines, budgets, and any potential risks or issues. Communication is a critical change management process as it can influence how stakeholders perceive the change and how they react to it.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...