Question #: 39
Topic #: 1
[All PK0-005 Questions]

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

  • A. Exploit the risk.
  • B. Accept the risk.
  • C. Avoid the risk.
  • D. Transfer the risk.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
r8derfan33
Highly Voted 1 year, 6 months ago
Selected Answer: A
Negative Risks Strategies: Avoid Transfer Mitigate Accept Positive risks Strategies: Exploit Enhance Share Accept Since this is an opportunity, that's a positive risk therefore Exploit is the answer.
upvoted 5 times
...
TheFai
Most Recent 7 months, 2 weeks ago
Selected Answer: A
Opportunity is a positive risk. You exploit those.
upvoted 1 times
...
IHateScreenNamesMore
1 year, 1 month ago
Selected Answer: A
Huh, It's A, because there are positive risks that can generate happy endings, like completing a project early, taking advantage of a byproduct, a chance to work together uninterrupted, partner with another team or organization.
upvoted 1 times
...
JohnLarsen
1 year, 2 months ago
Selected Answer: A
If an opportunity has emerged, the best action generally is to "Exploit the risk" (Option A), assuming that doing so aligns with the project's objectives and stakeholders' interests. Exploiting the opportunity allows the project to benefit from it, which could mean finishing under budget, ahead of schedule, or with higher than expected quality or customer satisfaction.
upvoted 1 times
...
jksdbfb
1 year, 2 months ago
Selected Answer: A
In the middle of a project life cycle, when an opportunity emerges, the best action for the project manager would be to exploit the risk.
upvoted 1 times
...
7acdde5
1 year, 6 months ago
Selected Answer: A
A is correct
upvoted 2 times
...
qjgkdsjflksjn
1 year, 6 months ago
Selected Answer: A
For sure it's A, why the hell would you transfer an opportunity?
upvoted 2 times
...
SkylarC
1 year, 6 months ago
Selected Answer: A
A. Exploit the risk is the BEST action for the project manager to take if an opportunity emerges in the middle of a project lifecycle. Opportunities are positive risks (also known as opportunities) that can have a beneficial impact on the project. When opportunities emerge, the project manager should take advantage of them by exploiting them. Exploitation involves changing a project management plan in order to enhance the probability of achieving the opportunities. For example, a project manager could assign more resources, speed up a process, or take other proactive measures to exploit the opportunity and maximize the benefits.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago