A change control log is used to track any changes made to a project, including unexpected events like a hurricane that significantly impacts the project schedule or deliverables. It documents the reason for the change, the impact of the change, the proposed solution, and the approval process.
Issue log. It is the realization of a risk (inclement weather) which created an issue (schedule delay). Change control log would only be necessary if you begin to implement a change to the schedule.
The project manager should use a change control log to document the effects of the hurricane delay on the project. A change control log is a tool that records and tracks any changes that occur during the project lifecycle. It usually includes information such as change ID, description, impact, status, approval, and resolution. A change control log can help to monitor and manage the changes that affect the project scope, schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and stakeholder expectations.
An issue is something that happened that you do not have control over. An issue log tracks and manages issues. - pg. 327 "The Official CompTIA Project+ Guide (PK0-005)"
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Palisades
2 months, 2 weeks agoTheFai
7 months, 2 weeks agodumantro
11 months agoBlueMan93
1 year, 6 months ago