exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 9 discussion

Actual exam question from CompTIA's PK0-005
Question #: 9
Topic #: 1
[All PK0-005 Questions]

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  • A. Update the work breakdown structure.
  • B. Review the backlog.
  • C. Seek baseline approval.
  • D. Establish the resource pool.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lamborghini
Highly Voted 1 year, 6 months ago
Selected Answer: C
The next step in the process is to seek baseline approval. The work breakdown structure (WBS) is a deliverable-oriented hierarchical decomposition of the total scope of work to be executed by the project team to accomplish the project goals and create the required deliverables. The backlog is a list of all the work that needs to be done in order to complete the project. It is typically organized by priority and due date. The resource pool is a list of all the resources that are available to the project team. This includes people, equipment, and materials. Once the PM has defined tasks, durations, resources, and costs, they need to seek baseline approval from the project stakeholders. This is a formal process that ensures that everyone is on the same page and that there is a clear understanding of the project scope, schedule, budget, and risks. Once the baseline is approved, the project can move into the execution phase.
upvoted 7 times
...
TheFai
Most Recent 7 months, 3 weeks ago
Selected Answer: C
You've essentially created the project schedule at this point, now you just need to get it approved.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago