Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

  • A. Gantt chart
  • B. Maintenance window schedule
  • C. Functional requirements
  • D. Test results
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 2 weeks ago
Selected Answer: A
Gantt chart is a chart that displays the Project Schedule.
upvoted 1 times
...
HumHalla
1 year, 4 months ago
Selected Answer: A
A Gantt chart is like a big calendar for your project. Imagine you have a school project that has different parts - like research, writing, and creating a presentation. A Gantt chart helps you plan out when you should start and finish each part.
upvoted 2 times
...
7acdde5
1 year, 6 months ago
Selected Answer: A
Vote for A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago