Exam PK0-005 topic 1 question 24 discussion

Actual exam question from CompTIA's PK0-005
Question #: 24
Topic #: 1
[All PK0-005 Questions]

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

  • A. Time and materials contract
  • B. Master service agreement
  • C. Fixed-price contract
  • D. Statement of work
  • E. Cost-plus agreement
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 3 weeks ago
Selected Answer: A
Time & Materials makes the most sense. Since both time & materials are both unknowns, doing a fixed price contract or a cost-plus agreement doesn't make much sense. SOW and MSA aren't contract types, they outline the work.
upvoted 1 times
...
lamborghini
1 year, 6 months ago
Selected Answer: A
The answer is A. Time and materials contract. A time and materials contract is a type of contract where the contractor is paid for the time they spend working on the project and the materials they use. This type of contract is often used for short-term projects where the duration and cost cannot be accurately estimated in advance. The other options are not as suitable.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago