A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Time & Materials makes the most sense. Since both time & materials are both unknowns, doing a fixed price contract or a cost-plus agreement doesn't make much sense. SOW and MSA aren't contract types, they outline the work.
The answer is A. Time and materials contract.
A time and materials contract is a type of contract where the contractor is paid for the time they spend working on the project and the materials they use. This type of contract is often used for short-term projects where the duration and cost cannot be accurately estimated in advance.
The other options are not as suitable.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
7 months, 3 weeks agolamborghini
1 year, 6 months ago