A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
B. RACI - This stands for Responsible, Accountable, Consulted, and Informed. It's a matrix used to clarify the roles and responsibilities in a particular process or set of tasks. In the context of project management, a RACI matrix shows the relationships between tasks and the individuals or teams assigned to them, indicating who is responsible for performing the task, who is accountable for the task's completion, who needs to be consulted, and who should be informed about the task's progress and results.
Given the options and the need to identify which resources are responsible for which tasks, the RACI matrix (option B) is the most suitable choice.
RACI is commonly used to define and communicate roles and responsibilities within a project. It helps clarify who is responsible for completing each task, who is accountable for its success, who needs to be consulted, and who should be kept informed.
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
7 months, 3 weeks agoDanYendler2014
1 year agojksdbfb
1 year, 2 months agolamborghini
1 year, 6 months ago