A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)
Issue Log & Change Log. Defect Log is the same as an Issue Log (and I can't find any reference to this in my Sybex book.) Issue log because its an issue. Change log because they did essentially an emergency change.
Issue log and change log are documents that should be used to record the event where the project team has just experienced an unexpected event and implemented a work-around. An issue log is a document that tracks and records any issues or problems that arise during a project and how they are resolved. An issue log can help to monitor and control the project performance and quality and prevent any negative impacts on the project objectives and deliverables. A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. A change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
Issue log and change log are documents that should be used to record the event where the project team has just experienced an unexpected event and implemented a work-around. An issue log is a document that tracks and records any issues or problems that arise during a project and how they are resolved. An issue log can help to monitor and control the project performance and quality and prevent any negative impacts on the project objectives and deliverables. A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. A change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
The project team should record the unexpected event in the Issue log and the Change log.
The Issue log is a document that is used to track and manage project issues. It includes information such as the issue description, the date the issue was raised, the assigned owner, the status of the issue, and the resolution.
The Change log is a document that is used to track and manage project changes. It includes information such as the change description, the date the change was requested, the assigned owner, the status of the change, and the impact of the change.
By recording the unexpected event in the issue log, the project team can track the progress of the issue and ensure that it is resolved in a timely manner. By recording the unexpected event in the change log, the project team can track the impact of the change on the project schedule and budget.
The other options are not as relevant.
A Risk report is a document that is used to identify and assess project risks.
A Defect log is a document that is used to track and manage project defects.
A Backlog is a list of work that needs to be done.
A Progress report is a document that is used to track the progress of a project.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
7 months, 2 weeks agosheilawu
1 year, 3 months agoTheGinjaNinja
1 year, 6 months agoTheGinjaNinja
1 year, 5 months agolamborghini
1 year, 6 months ago