Its D. How can I use this to study when I hit mistake after mistake after mistake after mistake?
Agile is especially necessary when you have to work your way through one unknown after another to hit the finish line so you can't fully define the specs up front.
i think the benefit of this site is that it offers questions and you choose the correct ones so that when taking an exam u have seen these questions before.
Multiple undefined tasks would favor using the agile methodology to manage an upcoming project. Agile methodology is a project management framework that breaks projects down into several dynamic phases, commonly known as sprints. Agile methodology is an iterative and adaptive approach that allows teams to respond to changing requirements and customer feedback quickly and effectively. Agile methodology is suitable for projects that have multiple undefined tasks, as it enables teams to prioritize and deliver the most valuable features first, and refine and improve them over time based on user input and testing
It's D. One of the best use cases for agile project's is project's that have multiple undefined tasks. Source: CompTIA CertMaster PK0-005
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
7 months, 2 weeks agoIHateScreenNamesMore
1 year, 1 month agomaps7
10 months agoshakevia463
1 year, 4 months agoTheGinjaNinja
1 year, 6 months agomax319
1 year, 6 months ago