exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 53 discussion

Actual exam question from CompTIA's PK0-005
Question #: 53
Topic #: 1
[All PK0-005 Questions]

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

  • A. Strong projectized organization
  • B. Medium risk
  • C. Lack of resources
  • D. Multiple undefined tasks
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 2 weeks ago
Selected Answer: D
Agile is iterative and would best respond to multiple undefined tasks. It is also good for projects that have an amount of risk to them.
upvoted 1 times
...
IHateScreenNamesMore
1 year, 1 month ago
Selected Answer: D
Its D. How can I use this to study when I hit mistake after mistake after mistake after mistake? Agile is especially necessary when you have to work your way through one unknown after another to hit the finish line so you can't fully define the specs up front.
upvoted 1 times
maps7
10 months ago
i think the benefit of this site is that it offers questions and you choose the correct ones so that when taking an exam u have seen these questions before.
upvoted 1 times
...
...
shakevia463
1 year, 4 months ago
Selected Answer: D
Multiple undefined tasks
upvoted 1 times
...
TheGinjaNinja
1 year, 6 months ago
Selected Answer: D
Multiple undefined tasks would favor using the agile methodology to manage an upcoming project. Agile methodology is a project management framework that breaks projects down into several dynamic phases, commonly known as sprints. Agile methodology is an iterative and adaptive approach that allows teams to respond to changing requirements and customer feedback quickly and effectively. Agile methodology is suitable for projects that have multiple undefined tasks, as it enables teams to prioritize and deliver the most valuable features first, and refine and improve them over time based on user input and testing
upvoted 4 times
...
max319
1 year, 6 months ago
It's D. One of the best use cases for agile project's is project's that have multiple undefined tasks. Source: CompTIA CertMaster PK0-005
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel