An administrator has submitted a change request for an upcoming server deployment. Which of the following must be completed before the change can be approved?
By going through the Change Management Processes:
- Request Forms
- Purpose of the change
- Scope of the change
- Risk analysis
- Change board and approvals
- End user acceptance
Thus, it is A: Risk Analysis as this step must be completed before approvals.
By going through the Change Management Processes:
- Request Forms
- Purpose of the change
- Scope of the change
- Risk analysis
- Change board and approvals
- End user acceptance
Thus, it is A: Risk Analysis as this step must be completed before approvals.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.220-1102 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Wiz_tech101
Highly Voted 1 year agoEngAbood
8 months, 3 weeks agomohdAj
Most Recent 5 months, 2 weeks agoWiz_tech101
1 year ago