Exam PK0-005 topic 1 question 72 discussion

Actual exam question from CompTIA's PK0-005
Question #: 72
Topic #: 1
[All PK0-005 Questions]

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

  • A. Dashboard
  • B. Gantt chart
  • C. Work breakdown structure
  • D. Requirements Traceability Matrix
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ajjrp18
Highly Voted 1 year, 7 months ago
it isnt B, I chose A because while a Gantt chart is a useful project management tool for tracking and visualizing the progress of tasks and their dependencies over time, it may not be the most suitable tool for updating the project sponsor and senior stakeholders about the overall progress of a project. Gantt charts can be complex and may contain too much detailed information for stakeholders who are interested in a high-level overview of the project's status. On the other hand, a dashboard provides a concise, high-level view of the project's status, including key performance indicators, risks, and other critical information. Dashboards are designed to be easily understood and can quickly convey the project's health and status to stakeholders. Therefore, a dashboard would be the most likely tool for a project manager to use when updating the project sponsor and senior stakeholders about the project's progress.
upvoted 7 times
...
ajjrp18
Highly Voted 1 year, 7 months ago
Selected Answer: A
A. Dashboard A project manager is most likely to use a dashboard to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a visual tool that provides a high-level overview of the project's status, including key performance indicators (KPIs), progress, risks, and other important information. Dashboards are designed to be easily understood and can quickly convey the project's health and status to stakeholders, making them an effective communication tool for project updates.
upvoted 5 times
...
mrdavy
Most Recent 11 months, 3 weeks ago
Selected Answer: A
Every stake holder wants to look at the overall and not the nitty gritty detail that Gnatt would show.
upvoted 1 times
...
2f0b60f
1 year, 3 months ago
Selected Answer: A
For updating the project sponsor and senior stakeholders about the progress of a project, the project manager would MOST likely use "A. Dashboard." Dashboards are visual tools that provide a high-level view of key project metrics and can be easily understood at a glance. They are often used to display the current status of project elements like schedule, budget, and risks, making them an effective tool for communicating with senior stakeholders who may not require the detailed, task-level information that other tools provide.
upvoted 1 times
...
sheilawu
1 year, 4 months ago
Selected Answer: A
project dashboard A tool that gives stakeholders and team members a quick look at the overall project. The dashboard includes the project’s status reports and may include other components such as key performance indicators, project metrics, project progress, and details of other project issues.
upvoted 1 times
...
sheilawu
1 year, 5 months ago
Selected Answer: A
I agree with A.Dashboard Project management tools can help you communicate project progress more efficiently and effectively. Project management tools can help you plan, track, and report on the project activities, deliverables, milestones, resources, risks, and issues. They can also help you collaborate with your team and stakeholders, and share relevant information and documents. Some examples of project management tools are Jira, Trello, Asana, Basecamp, and Microsoft Project. You should choose the tools that best fit your project needs and budget, and that are easy to use and access for your stakeholders. https://www.fool.com/the-ascent/small-business/project-management/articles/project-management-dashboard/
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.