C - Activities with zero duration are called "milestones." Milestones represent significant points in a project's timeline that mark the completion of a specific phase, task, or deliverable. They do not require any time to complete since they are essentially events that indicate the achievement of a certain goal.
A
The critical path method (CPM) is a technique that’s used by project managers to create a project schedule and estimate the total duration of a project.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
jksdbfb
9 months, 1 week agosheilawu
9 months, 3 weeks agoTheGinjaNinja
1 year agoSMOKEY87
1 year ago