exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 73 discussion

Actual exam question from CompTIA's PK0-005
Question #: 73
Topic #: 1
[All PK0-005 Questions]

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

  • A. Critical paths
  • B. Resources
  • C. Milestones
  • D. Work breakdown structures
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
9 months, 1 week ago
Selected Answer: C
C - Activities with zero duration are called "milestones." Milestones represent significant points in a project's timeline that mark the completion of a specific phase, task, or deliverable. They do not require any time to complete since they are essentially events that indicate the achievement of a certain goal.
upvoted 2 times
...
sheilawu
9 months, 3 weeks ago
Selected Answer: C
milestones as zero-duration tasks
upvoted 1 times
...
TheGinjaNinja
1 year ago
Selected Answer: C
Milestones have zero duration because they represent a significant point or event on the project. All other choices are made-up terms.
upvoted 3 times
...
SMOKEY87
1 year ago
A The critical path method (CPM) is a technique that’s used by project managers to create a project schedule and estimate the total duration of a project.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...