During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

  • A. Work with the project scheduler to update the project timeline.
  • B. Communicate to the stakeholders about the updated timeline.
  • C. Ask the development team to fast-track upcoming activities.
  • D. Add two resources so the critical activities will finish on time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 2 weeks ago
Selected Answer: A
They'd update the timeline and THEN communicate with Stakeholders about the new timeline, not before.
upvoted 2 times
...
utied
8 months, 4 weeks ago
Selected Answer: A
The MOST likely is find out the new timeline. You don't know what to tell the stakeholders other than it's gonna be late. Find the updated timeline, then tell the stakeholders how much delay they can expect.
upvoted 3 times
...
Narobi
1 year ago
Selected Answer: B
I would say the PM needs to communicate with stakeholders about the updated timeline since that falls under their responsibilities and is appropriate for the given scenario.
upvoted 1 times
Narobi
1 year ago
I see the argument for A though and believe it is a valid answer as well. If someone finds a quote from their book that would be great.
upvoted 1 times
...
...
sheilawu
1 year, 2 months ago
Selected Answer: A
A project scheduler develops and maintains the project schedule and works to ensure that resources are available when needed.
upvoted 1 times
...
TheGinjaNinja
1 year, 5 months ago
Selected Answer: A
Work with the project scheduler to update the project timeline. The project manager should work with the project scheduler to update the project timeline after finding an unforeseen dependency on one of the critical project activities that will most likely cause a delay. The project scheduler is a person or a tool that helps plan, schedule, monitor, and control the project activities and resources. The project scheduler can help the project manager to assess the impact of the dependency on the project schedule and identify any possible ways to mitigate or resolve it. The project scheduler can also help to update the project timeline with the revised dates and durations of the project activities and communicate them to the relevant stakeholders
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago