The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?

  • A. Host a risk workshop with all stakeholders to complete an initial risk assessment.
  • B. Work with the interns to develop a work breakdown structure and project schedule.
  • C. Conduct a skills assessment to determine the strengths and weaknesses of the staff.
  • D. Assign the resources to project tasks and encourage them to begin work immediately.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
95d3b92
2 months, 2 weeks ago
Selected Answer: C
How can you create a WBS without assessing their skills first? C is the makes the most sense.
upvoted 1 times
...
044f354
2 months, 2 weeks ago
Selected Answer: C
A: Risk assessment is important, but team skills should be assessed first; if only to understand whether the interns impose risk based on skills or lack thereof. B: WBS and schedule creation is premature without understanding team skills. Also the interns would not likely be primary participants in the creation of the WBS and project schedule, assuming neither exist yet. [CORRECT] C: Assessing skills is crucial before assigning tasks to new team members. D: Assigning tasks without knowing skills is ineffective and potentially harmful to project success.
upvoted 1 times
...
Therealjosh
6 months, 1 week ago
Selected Answer: B
Given the context provided, the most appropriate next step for the project manager would be: B. Work with the interns to develop a work breakdown structure and project schedule. Since the sponsor has indicated that the summer interns are authorized to work on the project, it's important to involve them in the initial planning phase. Collaborating with them to develop a work breakdown structure (WBS) and project schedule would be a constructive use of their time and would help in aligning everyone involved with the project's objectives and timelines. This step also ensures that the interns are actively engaged and contributing to the project from the outset.
upvoted 2 times
044f354
2 months, 2 weeks ago
WRONG. The WBS and Schedule already exist. PM must assess and determine how to most effectively employ these resources.
upvoted 1 times
...
...
hardware69
7 months ago
B. Sponsor indicated that the recently hired summer interns are authorized to work. Nothing about the staff is talked about. Do not over think these questions.
upvoted 2 times
044f354
2 months, 2 weeks ago
WRONG. The WBS and Schedule already exist. PM must assess and determine how to most effectively employ these resources.
upvoted 1 times
...
...
AdmiralGimme
7 months, 1 week ago
Selected Answer: B
You don't need to know the strengths and weaknesses of the staff, you know them. You want to know the interns abilities and where to place them, so B work with the interns.
upvoted 1 times
044f354
2 months, 2 weeks ago
WRONG. The WBS and Schedule already exist. PM must assess and determine how to most effectively employ these resources.
upvoted 1 times
...
...
Frosted
8 months, 1 week ago
The wording makes it seem that they're talking about the interns so question C seems iffy? Would interns be considered staff members in this context? If not, then B seems more correct.
upvoted 1 times
...
2f0b60f
1 year, 1 month ago
Selected Answer: C
The correct answer is C. Conduct a skills assessment to determine the strengths and weaknesses of the staff. The project manager should first conduct a skills assessment to determine the strengths and weaknesses of the staff. This will help the project manager to assign the interns to tasks that are a good fit for their skills and experience. It will also help the project manager to identify any training or mentoring that the interns may need.
upvoted 4 times
...
TheGinjaNinja
1 year, 5 months ago
Selected Answer: B
Working with the interns to develop a work breakdown structure (WBS) and project schedule is the next logical step. The WBS breaks down the project into smaller, manageable components, outlining the tasks and deliverables required for successful completion. Collaborating with the interns to develop the WBS will help ensure their understanding of the project's structure and scope.
upvoted 2 times
044f354
2 months, 2 weeks ago
WRONG. The WBS and Schedule already exist. PM must assess and determine how to most effectively employ these resources.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago