During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
I read other people's comments on C and barely any on B. I don't see how communications relate to confidence and alignment vs QA definitely relates to confidence and alignment more .
During brainstorming meetings, identifying techniques to ensure confidence and alignment with the project scope and goals is directly related to quality assurance. Quality assurance focuses on ensuring that the project deliverables meet the required quality standards and align with the project scope and goals.
From AI source...
B. Communication.
A communication plan is essential for outlining how project information will be shared, ensuring that all team members are informed, aligned, and confident in their understanding of the project’s objectives and their roles in achieving them. It typically includes the types of information to be communicated, the methods for dissemination, the frequency of communication, and the parties responsible for the various communication tasks.
The project manager will use the tools and techniques outlined in the
quality assurance plan to help monitor KPPs and KPIs. Quality control
issues that are identified may require a project change to ensure that
deliverable quality is maintained as set forth in the project management
plan.
Quality assurance is the process of ensuring that the project's deliverables and outcomes meet the defined standards and requirements. It involves activities that focus on preventing defects and errors, as well as verifying and validating the project's processes and deliverables. By identifying multiple techniques to ensure confidence and alignment with the project scope and goals, the project manager is establishing a plan to monitor and control the quality of the project throughout its lifecycle.
A communication plan outlines the strategies, methods, and tools that will be used to facilitate effective communication within a project. It ensures that project stakeholders, team members, and other relevant parties receive the necessary information in a timely and appropriate manner.
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Skydragon208
5 months, 1 week agogorilla2001
6 months, 3 weeks agoeXhilarat3d
11 months agojksdbfb
1 year, 8 months agosheilawu
1 year, 9 months agoHeatherrr
1 year, 10 months agoTheGinjaNinja
1 year, 11 months agojksdbfb
1 year, 8 months ago