Exam PK0-005 topic 1 question 85 discussion

Actual exam question from CompTIA's PK0-005
Question #: 85
Topic #: 1
[All PK0-005 Questions]

During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?

  • A. Time-tracking log
  • B. Issue log
  • C. Statement of work
  • D. Risk register
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Therealjosh
7 months, 2 weeks ago
Selected Answer: A
The PM is presenting the data that shows the contractor went over there time. so there for he will be using the Time tracking log that he will use to present to management.
upvoted 1 times
...
FloTown
9 months, 2 weeks ago
This is under topic 11A of Comp's study material there is definitely Time Tracking.
upvoted 1 times
...
Jay_Bee14
1 year, 1 month ago
Time-­ tracking tools are used to keep track of the amount of time team members are spending on tasks. You can use this information to update the project schedule and perform schedule variance calculations and forecasts. Heldman, Kim. CompTIA Project+ Study Guide : Exam PK0-005
upvoted 2 times
...
Realiable_0
1 year, 1 month ago
Selected Answer: B
It's B, There is no such thing as Time-Tracking Log in Project+.
upvoted 2 times
throughthefray
7 months, 2 weeks ago
They may call it "Application for Time Tracking" in certain materials but its definitely a thing.
upvoted 1 times
...
...
2f0b60f
1 year, 3 months ago
Selected Answer: A
The answer is A. Time-tracking log. The time-tracking log is the most accurate record of the contractor's overtime hours. It will show the exact dates and times that the contractor worked overtime, as well as the reason for the overtime. This information is essential for the management team to understand the extent of the issue and to take appropriate action. The issue log is not the best tool to use in this case because it is used to track known issues that are affecting the project. The overtime hours are not an issue yet, but they could become an issue if they are not addressed.
upvoted 3 times
...
Dar87
1 year, 4 months ago
Selected Answer: A
This is a time and work issue, so it belongs to time tracking
upvoted 1 times
...
ITSuffering
1 year, 6 months ago
Selected Answer: A
This should be A. As the Time-Tracking log will contain the information of the contractor putting in overtime. Not the issue log.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.