During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?
The most commonly used network diagramming method is the precedence diagramming method (PDM) . PDM uses boxes to represent the project milestones and arrows that represent activities. They also show the dependencies between the tasks.
Heldman, Kim. CompTIA Project+ Study Guide : Exam PK0-005, John Wiley & Sons, Incorporated, 2022. ProQuest Ebook Central,
precedence diagram method (PDM) A method of showing dependencies
between tasks by connecting squares (tasks) with arrows that show the
direction(s) in which work must flow between the tasks.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Jay_Bee14
5 months, 3 weeks agoRealiable_0
5 months, 3 weeks agosheilawu
8 months, 3 weeks ago