A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
2f0b60f
Highly Voted 1 year, 5 months agojksdbfb
Highly Voted 1 year, 5 months agohardware69
Most Recent 10 months agoatamisk999
1 year, 5 months agousernaame
1 year, 1 month ago