Exam PK0-005 topic 1 question 100 discussion

Actual exam question from CompTIA's PK0-005
Question #: 100
Topic #: 1
[All PK0-005 Questions]

A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?

  • A. Ask the sponsor for additional funding to accommodate the request.
  • B. Escalate the request to the senior management team.
  • C. Advise that a change request would need to be approved.
  • D. Instruct the project team to set up the additional workstations.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
throughthefray
5 months, 3 weeks ago
Selected Answer: C
Letting the dep manager know that this isnt a decision that you can make yourself is the first thing you would want to do here.
upvoted 1 times
...
mrdavy
9 months, 4 weeks ago
Selected Answer: C
A change was made and a change request is needed.
upvoted 1 times
...
jksdbfb
1 year, 2 months ago
Selected Answer: C
C is correct as you need to always submit a change request if the cbange deviates from the original scope
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago