A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?

  • A. Proposed solution design
  • B. Preliminary scope statement
  • C. Responsibility assignment matrix
  • D. Initial budget baseline
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
8 months, 2 weeks ago
Selected Answer: B
B - After documenting the project objectives and success criteria, the next step in completing the project charter is to define the preliminary scope statement. This statement outlines the high-level boundaries and deliverables of the project, helping to provide a clear understanding of what the project will and will not involve. Once the scope is defined, other aspects like proposed solution design, responsibility assignment matrix, and initial budget baseline can be developed in alignment with the project's scope and objectives.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago