A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
B - After documenting the project objectives and success criteria, the next step in completing the project charter is to define the preliminary scope statement. This statement outlines the high-level boundaries and deliverables of the project, helping to provide a clear understanding of what the project will and will not involve. Once the scope is defined, other aspects like proposed solution design, responsibility assignment matrix, and initial budget baseline can be developed in alignment with the project's scope and objectives.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
jksdbfb
8 months, 2 weeks ago