During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?

  • A. Discuss the requests with the sponsor.
  • B. Prepare and send the information.
  • C. Assign this task to the project team.
  • D. Review the communication plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
2f0b60f
8 months ago
Selected Answer: D
A Communication Plan is a crucial project document that outlines how communication will be managed throughout the project. It specifies who needs what information, how the information will be communicated, and when to distribute it. By first reviewing the Communication Plan, the PM can identify the predefined communication needs and expectations, and then align the incoming requests with what has been planned. If the requests are not in alignment, the PM will have a basis for a conversation with stakeholders or the sponsor about potentially revising the Communication Plan.
upvoted 1 times
...
jksdbfb
8 months, 1 week ago
Selected Answer: D
D - The first step for the project manager should be to review the communication plan. This plan outlines how project information is communicated to stakeholders, including the frequency, format, and content of project reports. By reviewing the communication plan, the project manager can ensure that the requests from stakeholders align with the established communication approach. If necessary, adjustments can be made to the plan to accommodate the requests. This ensures that communication is consistent and aligned with the project's overall strategy.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago