exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 115 discussion

Actual exam question from CompTIA's PK0-005
Question #: 115
Topic #: 1
[All PK0-005 Questions]

Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?

  • A. Program manager
  • B. End user
  • C. Steering committee
  • D. Project sponsor
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
10 months, 1 week ago
Selected Answer: B
B - In most cases, internal issues and potential delays are handled within the project team and stakeholders before they are communicated to end users. This is to ensure that the right information is being passed along and also to provide time to find potential solutions or workarounds before involving the end user.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...