Question #: 117
Topic #: 1
[All PK0-005 Questions]

A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?

  • A. Establish a minimally viable product.
  • B. Prepare new knowledge base documentation.
  • C. Update the project baseline and schedule.
  • D. Periodically review vendor performance.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
11 months, 2 weeks ago
Selected Answer: B
B - When implementing a new system, it's crucial to provide users with resources to understand how to use it. A knowledge base or user documentation would have been helpful in this situation, as it could guide employees on how to use the new self-service benefits enrollment system, reducing the need for them to call the human resources team for assistance.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...