During a project sprint, an analyst explains multiple situations the team encountered after the previous day's sessions. The analyst then lists the tasks that need to be completed before the end of the day. Which of the following meeting types is the team utilizing?

  • A. Stand-up meeting
  • B. Workshop meeting
  • C. Kick-off meeting
  • D. Presentation meeting
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
11 months, 2 weeks ago
Selected Answer: A
A - The scenario described, where an analyst explains situations from the previous day and lists tasks to be completed, aligns with a stand-up meeting. Stand-up meetings are a common agile practice where team members provide brief updates on their progress, discuss any challenges or issues, and plan tasks for the day. The meeting is typically short, focused, and conducted while standing to encourage brevity and engagement.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...