exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 124 discussion

Actual exam question from CompTIA's PK0-005
Question #: 124
Topic #: 1
[All PK0-005 Questions]

A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the following tools should the project manager update NEXT?

  • A. Defect log
  • B. Stakeholder register
  • C. Issue log
  • D. Risk register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
11 months, 2 weeks ago
Selected Answer: D
The correct answer is indeed D
upvoted 2 times
jksdbfb
11 months, 2 weeks ago
In the scenario you described, where the probability of occurrence has increased for an item on the watch list, the appropriate tool for the project manager to update next would be the Risk Register. The Risk Register is a document that captures and tracks identified risks throughout a project. By updating the Risk Register with the increased probability, the project manager can ensure that the risk is properly monitored and managed..
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...